The project to modernize our Sands of Kahana elevators is now half complete as of this writing. Each elevator takes approximately two months. The work that began New Year’s Day on Elevator 4 was finished on February 28. The Elevator 3 renovation began on March 1 and was completed on April 30. Work began May 1 on Elevator 1 and is scheduled for completion by the end of June. Once finished, we will turn our attention to Elevator 2. By the time it is completed at the end of August, our entire fleet of elevators will be fully functional and ready for takeoff! Of course if you insist, you can still take the stairs.